Ilam Petrochemical Company · Chawar, Ilam
Keeping a whole complex alive.
Comprehensive operation, maintenance and overhaul of the entire Ilam Petrochemical Complex — 300,000 t/y HDPE, 460,000 t ethylene and 120,000 t propylene of production capacity entrusted to one contractor.
Project overview
Since July 2020 Kahroba Tavan has been the maintenance contractor of the Ilam Petrochemical Complex — winning the tender twice in open competition with the country's first-tier oil and gas contractors, and extending the engagement through three consecutive contracts worth over $30M in total.
The scope covers every discipline — mechanical, piping, civil, electrical and instrumentation — across every unit: the Olefin site, HDPE plant, sulfur recovery unit (SRU), utility, industrial wastewater, hydrogen unit, offsite, the ethylene line and the complex power plant.
Scope of work
Full-spectrum scope.
- Emergency, routine, basic and preventive maintenance of all units and equipment
- Comprehensive overhaul (annual major & minor) — repeatedly completed ahead of schedule
- Predictive maintenance: condition monitoring, vibration analysis, thermography and NDT
- Calibration and periodic testing of control systems and precision instruments
- Utility maintenance — power, water and compressed-air systems
- HVAC maintenance guaranteeing internal environmental conditions
- Spare-parts management to minimise shortage-driven downtime
- Troubleshooting and resolution of equipment failures and operational issues
Results
Key achievements.
- Production capacity and complex reliability successfully maintained
- Equipment uptime improved and maintenance costs reduced
- Annual overhauls of 2020, 2022 and 2023 finished ahead of the planned schedule
- Full compliance with safety and environmental regulations
- CMMS and APM software developed exclusively for the complex
- High customer satisfaction through timely, efficient service